Requirement date in Md04 to be adjusted


i have a component A* with lot size mb(monthly plan),plan on 01.12.2007 .

i used GR Processing time 5 days.To bring component in previous month i,e, on 26.11.207.

Now ,my problem is that due to mb lot size & GR time, the requirement/receipt date of the component is 01.12.2007 (minus GR time ).the basic finish date is 26.11.2007 .we have monthly planning & if we see in the COOIS report month wise it showing o.k.,(26.11.2007),but when we see in the MD04 the date in the requirement date is 01.12.2007 appearing that should be required 26.11.2007.How this date can be adjusted.