Hi Experts,

I had scenario in Sub-contracting, I’m purchasing the raw material from X vendor and send the same material to the sub-contracting vendor- Y for drilling the material. After receiving the Main Component (material) from the sub-contracting vendor- Y, we are doing the quality check. Now the material is in damaged, I want to send the damaged material to the X vendor (ie. To the purchasing vendor). How to do that?

Regards,

Sudhakar