Hi PP Gurus,
I am mapping the process & get lured into the authorization of goods issue of RAW materials.
After MRP run PR are automatically created for RAW materials due to 'control parameters' settings in MRP run screen. Now at the time of Production order release I want to issue the RAW materials for it. Who should do the goods issue, either PP user or MM user?
Thanks & regards,
Abu Arbab
Hi
At the tiome of order release Goods Issue is not a standard feature.
After release only GI can follow.
Authorization can be for MM user for material staging.
But actual issue ( movement type 261) will be for PP user.
Regards
YMREDDY
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
After creation of production order PP person should create reservation in transaction - MB21 then with reference of this reservation number MM person will do the goods issue with transfer posting activity trrough MB1B.
Reward this points if you find it useful.
regards,
Amit.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
14 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.