completion date for notification, IW22

when i tried to set the completion date for a notification through IW22 am not able to view the completion date and completion time inputs in the popup screen, only reference date and reference time is showing

can this be due any status set to that notification


hi varalakshmi

kindly check in the following path in IMG activites

Plant maintenance>Miantenance plan work center>Maintennace plan>Miantenance plan category

in that under different categories there will be a column <b>confirmation date</b>

if this is the selected then seperate completion date will be generated for completion of maintenance call object.Kindly select that field and press F1 you can find detailed information on this