Hi, I want to post Goods Receip from scheduling agreements. I have this mistake (dokument has no notification. Item M7064). can you help me please?
Hi Dede,
Please check in your PO in item detals you have set confirmation contrl
Remove that system will not ask for notification
BR
Diwakar
reward if usel
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Open scheduling agreement or its delivery schedule (ME32L or ME38) and verify its item details if there is confirmation control key defaulted. Remove the confirmation control key if your business process allows. If it is required for your process, don't remove but you process inbound delivery / Shipping Notification from VL31N first. Then, you will be able to process GR. Note: You will be able to process GR for a scheduling agreement only if there are open delivery schedules available (and in your case shipping notification is to be processed by retaining the confirmation control key).
Hope, it clarifies
Hi,
For GR to be done for a Schd Agree, check the date of your delivery scedule line and date of GR ( within tolerances )
Anand
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.