Hello All

Current unif of Measure is "PC" in our master data and schdule agreemetent.

So I have defined new conversiton factor like 1 roll 1000 Pc; becouse I will order it from our supplier as Roll but Good receipt will be done as a PC..

what should I change in schdule agreement and material master...

thank you for your help

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

In material master u will hve to put ordering unit as roll in purchasing view

and for Scheduling agre i dont khink u will be able to change unit or measure

reward if usefull

Former Member
0 Kudos

Hi

You mean that when we maintain material master it will be enogh and

when we release the schedules supplier can see order as a roll instead of PC

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Yes once you mention in the material master, need not do it in Sched agree, while doing GR, it shows entry in both the units of measurement.

Anand