cancel
Showing results for 
Search instead for 
Did you mean: 

routing not found

Former Member
0 Kudos

Hi friends,

i have created routing for finish product .in MTO senario i went for MRP RUN after sales order is entered. .the corresponding planned order is created . but when itry to convert the planned order to production order a message is coming like <b>routing not found</b>.

so please syuggest what to do?its urgent

feasible answer will be awarded

THANKS & REGARDS

OM

Accepted Solutions (1)

Accepted Solutions (1)

former_member196398
Active Contributor
0 Kudos

OM,

Check whether the routing is having valid status and Usage 1 or 3 - Status - 2 or 4. This you can check in the routing header.

Also check the validity based on Lotsize , whether the sale order quantity is within lotsize mentioned in the header of the routing.

Also check the Validity start date of the routing in the header, the Plannned order start date should be latter than the routing valid start date.

Regards,

Prasobh

Former Member
0 Kudos

Hi prasobh,

thanks a lot for your reply.

my problem is solved.

om

Answers (3)

Answers (3)

Former Member
0 Kudos

Om,

Check out what is the Routing selection in OPL8,

Check out whether the routing created is valid on the date and lot size,

Sumeet

Former Member
0 Kudos

There can be reasons like

- Valid date for the routing is not within the date range where you created the Order

- Routing Quantity Range is different from the Order quantity

- Routing usage is given different other than production

- Routing status is only defined as Created or Release for Costing.

Please check the above possibilities, May be this can help.

Former Member
0 Kudos

Hi Omkar,

Go to Routing header data & check lot size maintained in CA02 & compare it with

material lot size used while creating sales order or MRP RUN.

Also check unit of measurement of both.

Message was edited by:

PRADEEP