Dismantling handled through Sub Contracting ...

Former Member
0 Kudos

Hi Gurus,

How to handle a dismantling of an item through Sub contracting scenario ?

say .. I want a particular item to be dismantled which I provide it to a sub contractor & I want to receive the child items into my system..

Kindly provide me how this scenario be captured in detail.

Thanks

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hello Nainar

Chk whether I have understood your problem correctly -

You are sending a machine (M1) to a subcontractor for dismantling into spares.

You will be receiving some of the spares (SP1, SP2) back.

In this case, create Subcontractor purchase order for SP1 with item category "L" and enter M1 as component manually.

This process will help you to consume M1 and stock of SP1 will be build.

There is a standard process of byproducts but if we it then we will have stock of both M1 as well as SP1.

Regards

Rajesh

Do reward if useful...

Former Member
0 Kudos

> Hello Nainar

>

> Chk whether I have understood your problem correctly

> -

>

> You are sending a machine (M1) to a subcontractor for

> dismantling into spares.

>

> You will be receiving some of the spares (SP1, SP2)

> back.

>

> In this case, create Subcontractor purchase order for

> SP1 with item category "L" and enter M1 as component

> manually.

>

> This process will help you to consume M1 and stock of

> SP1 will be build.

>

> There is a standard process of byproducts but if we

> it then we will have stock of both M1 as well as

> SP1.

>

> Regards

>

> Rajesh

>

> Do reward if useful...

Hi

Thanks for the response.

This is valid if there is only one spare which we get. how it wud capture all spares ( how the PO wud be ? )

Former Member
0 Kudos

Hi,

Create one material for dismantling preferably non stock Make Sub contracting PO send the assembled item.Receive all child items as by products.

Hope this helps

Thanks

suresh

Former Member
0 Kudos

Hi

Thanks for the reply

Can you please explain in detail..

Former Member
0 Kudos

Hi,

1.Create a material as told non stock material with description as dismantling of parent item.

2.Make Sub contract PO for this item and attach parent item as component.

3.Create a BOM for non stock material with all child items as by products.

4.Once u make GR all by products will come to stock.

Hope this clarifies.

Thanks

suresh

Former Member
0 Kudos

In this case , can you explain how the BOM would be ?

also more on Byproducts please ..

Thanks