Calculation of Over head in MO

Former Member
0 Kudos

Dear PM Guys,

In MO when overhead is calculated.

Iam finding in MO,under Tab Additional data,one field is there Named OBJECT CLASS with filled in value of OVERHEAD.From where its coming and what is the impact of cost showing in cost tab.

I request your to brief the things.

Regards

ISWARI

Accepted Solutions (1)

Accepted Solutions (1)

former_member187991
Active Contributor
0 Kudos

Hi

Generally Maintenance order are overhead only because it is indirectly assiting the production.Hence whatever cost involved in PM will be secondary cost since it is with respect to the cost center

The object class categorizes Controlling objects according to their business function and enables you to analyze cost flows within Controlling from different business perspectives.

<b>The following object classes are available:</b>

Overhead

Production

Investment

Profitability analysis and sales

While certain object types automatically belong to a particular class (for example, cost centers belong to the "Overhead" class), others need to be explicitly assigned to an object class in their master record (this is the case with internal orders and work breakdown structure elements, for example).

since we are settling against the cost center genreally MO will be overhead only

hope you have cleared

regards

thyagarajan

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear Mr Thiyagarajan,

Thanks for your reply.Pl clarify one thing

In my understading Over calculation for order is nothing but settlement of order

(as we have defined KO8G in background daily) to the cost center defined in MO.Eventhough if we made any goods reversal in MO after settlement it will reflect in costing tab but it wont reflect in CC,since it is already posted.To get it reflected in CC,we have to manually reverse the settlement of MO using KO88 and re-settle it again.

Is it right sir,

Regards

ISWARI.

former_member187991
Active Contributor
0 Kudos

hi iswari

Yes the process following is correct, but i recommed that finish all your process in MO and settle .because if you forget to resettlement then costing will be varied, also since the order is open someone can still use and the overhead calculated and amount settlement will be different .Hence please do the technical completion of the order and do the settlement run.

regards

thyagarajan