Maintenance order settlement

Dear Gurus;

I would like to know, how can I stop maintenance order to be settled before it is technically completed? I think, it would be more appropriate if order is settled when it is TECOed instead of in 'release status'. If I am wrong can you pls. suggest me the concept?

Points assured.

Thanks & Regards




there are 2 options to restrict settlement process.

1 create the User status "NSET" and configure the Business rules to stop settlement process. When you release the order set the user status to NSET. When the order is complete and ready to be settled , change the USER status.

2 Change the SAP statndar business rule for the System Status REL.

I would recommend you to go for option 1

Hope this Helps you