Hi folks
We are implementing BPC 5.1.
Previously we have used R3 transaction 7KEX to input budget data from Excel, but the business would like an automated upload from BPC. We would prefer not to create z-versions to work around the problem.
Does anyone have experience with automated budget uploads to R3, especially from OutlookSoft or BPC?
Regards
Russel
Hi Russel,
Unfortunately at the current time there is no automated method for retraction from BPC however this is a custom development. Right now the best way to do this is to use the method which you describe below.
1) Export your data from BPC 5.1 using the Data Manager
2) Import into R/3 using the Excel Budget data input.
Cheers,
Scott