BOM COMPONENTS

Hi ...

When i am trying to do a Subcontracting PO , for the Finished Material (BOM)

i am getting the message as " Not Possible to determine the BOM Components".

Can anyone please say me what are the checks to be followed in order for the

BOM to recognize its Components.

Regards

Balaji

Former Member
Former Member replied

Hi

If u want to create sub contracting orders through MRP then only u need to maintain 30 in special procurement

Item category 'L' is defined for subcontract. Based on this item category system identifies that this component is for subcontract

cheers!!

Vishal...