PS Report CN41

Dear PS gurus,

In CN41 Project Info System, selected ps profile 00000002, and given a project definition, below layout is under use :

Project Object : Project Description

Project Object : Project codes ( project definition, WBS, Network)

Start (B) : date is displayed

Finish (B) : date is dispalyed

Actual duration : nothing displayed

Start ( A) : date is displayed

Finish (A) : date is displayed

Duration : nothing displayed

can u pl let us know why actual duration & duration - days are displayed in both.

pl help how the duration is displayed at cn41.

pl help




Hi Srihari,

Kly recall teletalk we had.

I repeat what I explained earlier:

Confirmation of assigned activities will update the following date fields in the WBS element( provided "no date update" is not selected in the confirmation transaction):

1) Tentative actual start date

2) Tentative actual finish date

For tansferring these dates as actual dates, you can go ahead as below:

Logistics->Project System->Dates->Actual dates->Edit ->Reconcile dates- Determine actual dates.

Instead of the menu path, you can execute the transaction code: CJ25

Input the project ID or WBS, select activity radio button and execute. This will open-up the entire structure. Select the WBSE for which you want to transfer dates from tentative to actual. Then edit->reconcile dates->determine actual dates

With this tentative dates will be transferred as actual dates and actual duration also will get updated.

Hope thie solves your problem.

If so, kindly acknowledge the same.