Hi All,
I want to refer a PR to a PO. Also i want the system to refer only the subline item i.e., the service. My scenario is when i refer a service PR which is having a main line item and 10 sub line items and if i make a single PO by referring that Pr for only 5 subline items and if i try to create another PO for rest of the 5 sub line items the sytem is not allowing. It is saying that PR had already been ordered fully
Pls help me out.