on 11-20-2007 6:34 PM
Hello Folks,
We are performing transfer and process on the same day and doesnt involve any changes in the status. Once we perform the transfer and subsequently pay changes, the system confirms that it deletes the earlier record and once we confirm, it deletes the previous transfer record and overwrites with pay changes record.
I tried removing the status, it allows to record two actions, but the earlier record doesnt have the end date and the pay changes (latest record) is having the end date (31/12/9999).
Appreciate the inputs.
Regards
KK
Hai.
pls check the Function what u have included in the info group.....
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Folks,
Thanks much for the response.
FC is "other actions" and am unable to understand why the records are not getting stored in 0302?
TC is "3".
We have 0302 to get additional actions stored and unsure why the records are overwriting and the latest record getting stored. I am afraid to ask the user to go to SE11 and check for 0302 records.
Appreciate more inputs while i on my task to get the same fixed.
Regards
KK
Hi,
And also look of for the time constraint on the infotype
ok
Reward if applicable
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello KK
If you run two or more actions on same day the laterst is stored in IT-0000 the previous actions are stored in IT0302.
you can check table PA0302 in se11 for that pernr.
if you check PA0000 in se11 you will find only latest action record.
you cant view 0302 in PA30.
reward points if helpful
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.