MRP Run For Requirement Plan Number

Dear All,

Any User Exits available to run MRP based on Requirement Plan Number that means i want to run MRP only materials undergone that Req Plan Number.

Thanks & Regards,

S.Ganeshraja

Former Member
Former Member replied

Hi Ganesh,

I am unable to understand why u donot want to include previous plan, anyway if u dont want MRP to cosinder previous plan,

Goto Md62 -->Give requirement Plan Number->deselct the "version Active indicator" check box for particular material, Now this plan will not be included in MRP.

i hope this ill solve ur problem, Rewarding points, Encourages forum members

Regards

pradeep

0 View this answer in context