cancel
Showing results for 
Search instead for 
Did you mean: 

CM01

Former Member
0 Kudos

Hi all

Can any body brief me out whats the use of transaction CM01(Capacity Planning Selection).

Regards

Sandeep Patil

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi sandeep,

CM01 report Gives overview of workcenter load posotion and overload for a period. Here u can see the Avilable capacity of workcenter , Capacity Requirements for production, Remainning avilable capacity, if any over load it shows with " Red Mark"

if u found any overload u have to do the capacity levelling.

Lead time scheduling should be carried out to see requirements in CM01.

regards

pradeep

former_member646433
Active Participant
0 Kudos

Hi sandeep,

CM01 is use to plan your work center load. In this you get the total load on your work center which told about availble and load report if that work center is overloaded then you want to shift load or use CM21 for capacity leveling.

Hope this will help you and reward suitable points for every answered.

Regards,

Rajesh Tayade