on 11-19-2007 12:20 PM
Hallo everybody.
I´ve a question in Job theme.
I´ve scheduled SAP Jobs as note 16083.
But the job SAP_CCMS_MONI_BATCH_DP (scheduled hourly) takes very long, but not always:
on 02:14:31, 09:14:31, 14:14:31, 19:14:31, 00:14:31, 06:14:31, 11:14:31, 16:14:31...every 5 hours...
The others scheduled SAP_CCMS_MONI_BATCH_DP takes 1 or 2 seconds.
Why? Delay takes always 32-33 seconds.
What can i check?
I know that this job is not a reorganization job but is needed to start tools / methods in the system monitoring area (RZ20).
Thanks for help.
Points will be awarded for useful answers.
Alberto Di Fazio
solved see note 127642