on 11-17-2007 4:18 PM
Hi,
in material and vendor master there is the field "Planned deliv. time".
How are these hierarchical organized?
Best regards
Hi
Planned Delivery Time are maintained in 3 places
1)In Material Master, MRP 2 View
2)In Vendor Master, Purchasing Data View
3) In Info Record, Purchasing Org View
Actually, In Vendoe master what Pln.Del.Time you are giving is common for all the material supplied by the vendor....
In Material Master, MRP View what you are maintaining....based on this thing only, the "Replinshment Lead Time" of MRP Planning is calculated...( RLT is nothing but PR Processing time + Planned delivery Time + GR Processing time)
In Info Record What you are maintaining, it will be copied to PO
Rewrd if useful
Regards
S.Baskaran
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Planned delivery time in maintained in Inforecord/scheduling agreement,material master and vendor master
If u have activated it in OMDT for plant level planned delivery time is always calculated from info record/scheduling agreement
if not then from mm AND THEN FROM VM but planned delivery time from vendor master does not make sence as if vendor is supplying two material having two diff. lead times then how come PDT is same for both material based on VM
So one can say PDT hierarchichy is Info record and then MM
Vishal...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.