Capacity Levelling

Hi PP gurus,

While doing capacity leveling for production order,the machine capacity is dispatching to Work center but the labor capacity is not is showing the following errors

1 Capacity not available

2.No remaining available. cap. available in planning period

3 Planning step was undone (UNDO)

I have checked the particular Work center and routing all releated data's and settings.but still the labor capacity is not getting dispatch.

please guide me on this issue to clear.

thanks in advance