on 11-16-2007 9:37 AM
in the product planning table , Everytime you enter a forecast into
daily buckets, it jumps to the next day. If you work in weeks, it jumps
to the next week unless you use 5-day Display calendar (PPDS) in
location master. If you work in days , it jumps to the next day.
Just one more explanation that we are using the time zone as "Time Zone of the Location": without it, display in shifts is not correct.
kindly let me know how to resolve it so that there is no issue of jumping forecast.
Just to understand, do you see the jumping behaviour when the Time Zone is cleared in the location ? If not, then can you just for testing, try to clear calendar to see you get a jumping behaviour. Just trying to figure out what could be causing the exact problem. Are you using SAP standard calendars or custom ones ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.