Hi all,

I have 2 levels of production, 1st is semifinished and 2nd is finished (which uses the 1st as an input)

I want to relate the activities of these 2 orders such that for example,

if 1st order is from resource A, then 2nd order can be restricted.

can I use a transportation matrix from these resources or activities but they are not in the same order, they are predecessor and successor orders.