Hi PP Gurus,
please tell me how I can get operation/machine/resource downtime analysis in PPPI.
Regards
Abhik
Dear Abhik,
within SAP Standard this is not possible in R/3. See SAP note 381137
[...]
Reason and Prerequisites
SAP does not plan any further development of the Downtime functions on
the basis of the currently existing transactions.Therefore, the
functions were removed from the menu and may only be used in the test
system.
[...]
and
[....]
SAP does not accept any further support for already existing downtime
functions. There is no longer any aim to carry out implementation in
live systems and this not supported either.
[...]
If you have an APO system, you can use APO, here a downtime functionality is provided.
Regards,
Sabine
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.