How to do a Scheduling Agreement w.r.t MRP?

Thanks

Vineeth.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

You do not do a Scheduling Agreement w.r.t. MRP. You use an SA to create delivery schedules during MRP Run. You need to update the source list with the details and MRP run will take care of the rest.

Lakshman

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Vineeth,

Scheduling agreement is not done from MRP but in procurement sub module by strategic Purchasing Department. It is done in ME31L.

When a scheduling agreement is setup and if you assign MRP relevancy indicator 2 automatic delivery schedules, in source list for a material at the plant level and assign that scheduling agment in it, when MRP is executed, SAP will be able to create automatic delivery schedules for that material (referencing that schedling agreement that is assigned in the s/list).