Dear Consultants,

If we want budget for cost center we give the values in KPZ2. Here it is not checking for Availability check. I am trying to post more than the budgeted values, the system is taking without giving any message.

Could any one help me in putting some error/warning/info message when it crosses the budget.

Thanks in advance.

Kotte

Former Member