cancel
Showing results for 
Search instead for 
Did you mean: 

Delivery date proposal based on component availability

former_member666941
Participant
0 Kudos

Hi,

We use a third party subcontractor scenario, where item category TAB/sched line CB generate a sucontracting PO.

Is it possible to have availability check propose a delivery date based on component availability ?

Currently, the system only takes into account the delivery time field in the PO subcontracting info record, and does not take into account the stock situation of the components.

If anyone could point me in the direction of the appropriate settings, I would greatly appreciate it.

Regards

Ken

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello Ken,

There is a user exit which would meet your requirement, I don't remember it but you could find out by taking the help of ABAPER.

I remember in one of my projects I had exactly the same requirement, for which we had used User Exit.

You could view and change user exits as per your requirements using t code SMOD and CMOD respectively.

Reward if helpful.

Thanks

Murtuza

Answers (0)