on 11-13-2007 3:37 PM
Dear all,
we would like do an ATP check in the customer order with two steps:
1. Check against allocation (on a land/customer level)
The determinated date (found in bucket) should determinate the start of CTP
2. Start CTP against block planning using not the required delivery date of the customer order, but the date from the allocation check
Start CTP only if a quantity is found in the allocation check
Do not Start CTP if the allocation check is negative
Is this COMBINATION feasible in global ATP?
Tx
Stefan
Hi Stefan,
How did you solve this issue? We are facing the same decision and we broke it in two parts:
1) User exit in R/3 to check whether Allocation exists (we think to have an structure like the product alloction but a little more restricted).
2) Run CTP in APO
I will appreciate if you share your experience
Best Regards
-Italo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes, This combination is feasible in GATP.. May be you will require to use userexit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.