Good after noon friends... & Gurs..

Can any body expalin me about Budgets - control in SAP, please...

Points should be assigned..!

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

In SAP you have to terms.

1. Planning for planning you can have more versions

2. Budget.

For internal orders and PS (not cost center accounting) you set-up budgets (you can copy it from a plan version).

In the config you can say what you want to do with budget control.

What you say when 100% is spend sent an e-mail to the controler and when more then 115% is spend don't allow to create purchasing orders or posr orders on the project / internal order. It possible to exclude cost element for this. (example hours from cats)