Service PO qty as 1 not able to change

Former Member
0 Kudos

Dear all

While creating PO for service the qty field is taken by system as 1,not able to change the qty in po item overview level,Is their any solution for the above.

regards

M.Chandra mohan

Accepted Solutions (1)

Accepted Solutions (1)

former_member218067
Active Contributor
0 Kudos

Hi Chandra,

Services are always maintained below item level

so when you create service po default qty will be 1

You will have to go to service level in item details and maitain QTY unit and value

for services there it may in Hours or days etc.

Please check

BR

Diwakar

reward if useful

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Chandra

In item overview Services Qty. will be always taken as 1 it is std. SAP functionality

hence when you create service po qty will be always 1.and system will overwrite any value to 1

As in item detail u maintain details description and Qty of service

Vishal...