No MRP result for MD01

Dear All

When I take MRP run through MD01 system is not creating any purchase requisition but if I take MRP run for that material through MD02 it creates purchase requisitions.

I tried option of MD01 through NETCH, NEUPL,NETPL but nothing works.

Please let me know what may have gone wrong.

Rgds

Kiran

Former Member
replied

1. First try to create the planning file entry usingthe MD20 Or MDAB

2. Once you complete this go to the MD21 and check if you hvae plannig file entry

3. Now try to run the MD01

This will generate the MRP results.

4. The reason for this is When you run using the MD01 system will first check the planning file entry

Let me know the feedback