on 11-12-2007 2:14 PM
Hi experts,
I have different plants set up in a company code. Each plant has its own material requirements. I want to group some of these plants into a "Hub" and then analyze the material requirements.
Can anyone suggest how do I map this in SAP?
Jack
hi
when u r doing MRP for each plant u cant get total reqmts for all plants at once.
the only soluation is go to ME5A
give for which material & in which plants u want to know PR
then it will show all the PR s of material under those plants
then u can procure at a time .
if any otherway is possible please suggest me & him alos
nani
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nani
Thanks for your response. Grouping bthe plants during reporting is definetely one way of doing it...I found the report MCE7 to be very close to my requirement.
I am also thinking of defining each purchase organization for each group of plants if the above report does not satisfy the customer..
Thanks.
Jack
Jack,
If this is purely for reporting purposes, then the simplest way would be to create <i>variants</i> for each group of plants in MCE7 or other reports.
I don't think that defining purchasing orgs. purely for analyzing material requirements for a group of plants is a good idea. Purchasing Orgs. are meant to reflect your purchasing structure and nothing more.
Hope this helps.
H Narayan
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.