Networks in SAP PS Projects

Former Member
0 Kudos

Hi All,

Canyou please tell me whether it is better to use header assigned networks or activity assigned networks.

Muzamil

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Header assigned network is practically used only when the network is assigned to sales order line item - as in the case of assembly processing. In such situations, sales order line item is the controlling object.

Hence, if your scenario is not assembly processing, activity assigned network is the choice for you.

Regards

Muraleedharan.R

091 9880028904

murali_kangazha@yahoo.com

Former Member
0 Kudos

Hi Muzamil,

It depends on the requirement.

If you use Network with activity assignment, The cost can captured at activity level.

In case of Network with header assignment, The network will carry the cost (Sum of the activities cost).

Hope it is clear

Reward your points if useful.

Regards,

Prasad