4.6 C to ECC 6.0 Upgrade Project Timeline Sheet in MPP format

Former Member
0 Kudos

Dear all,

We are now proposing our customer for the 4.6c to ECC 6.0 Upgrade.

Our customer is currently in 4.6c/oracle 9i/HPUX 11 i. He wants to move to ECC 6.0.

If you have the project timeline for the above Technical Upgrade, can you pl send it to me.

If you don't have in MPP format atleast send me the Work Breakdown structure with timelines.

I shall modity the same to our customer and submit

Thanks & Regards

Senthil

j.senthilmurugan@gmail.com

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Thanks

Former Member
0 Kudos

If you have ASAP mpp file.pleae mail to me.

srikant_23@yahoo.co.in

Regards,

L Srikanthan.

Former Member
0 Kudos

Preparation Phase* 6 days

Kick Off Meeting 1 day

Upgrade Project Procedures Preparation 1 day

Prepare Upgrade Project Plan 1 day

Technical Requirements Assessment 3 days

Assess Training needs of Key-users & End-users 1 day

Prepare Detailed Basis Activity List for DEV, QA & PRD 1 day

Business Blueprint Phase 6 days

Develop System Landscape Upgrade Plan 1 day

Functional Requirement Checklist 1 day

ABAP Development check list 1 day

Develop detailed Training Procedures & Documentation for Key Users & End Users 1 day

Identify Testing Scope & Scenarios 1 day

Identify Authorizations Conversion to Roles for SAP ECC 6.0 2 days

Develop Documents as per Basis Activity List 1 day

Develop Authorization Matrix for Activity Groups to Roles Conversion 2 days

Prepare Upgrade Deliverables Checklist 1 day

Realization Phase 28 days

Installation of Solution Manager 3.2 System 1 day

Creation of New Development System for Upgrade Project (Homogenous System Copy - PRD) 2 days

Upgrade to AIX & Oracle 10g, SAP ECC 6.0 on New Development Server 3 days

Upgrade Frontend Software 4 days

Perform SPAU & SPDD Corrections 5 days

Perform ABAP Development & Corrections 10 days Perform Authorizations Conversions and corrections after upgrade 8 days

Perform Upgrade Testing for each Application Module 7 days

Perform Unit & Integration Testing 6 days

Perform Training to Key Users & End Users (Generic & Specific) 3 days

Upgrade to AIX, Oracle 10g, SAP ECC 6.0 on Quality System 1 day

Homogenous System Copy of PRD to New Quality & Upgrade to AIX, Oracle 10g & SAP ECC 6.0 2 days Perform Testing in Quality System 3 days

Testing by end users on Quality System 1 day

Production Realization & Go-Live Phase 6 days

Upgrade to Production System Operating System to AIX (after close of business hours - 23:00) 1 day

Oracle Upgrade to 10g (after close of business hours - 23:00) 1 day

SAP Release Upgrade to ECC 6.0(Downtime Minimized - Downtime occurs in non-business hours) 2 days

User Acceptance Testing 1 day

Production System Go-Live 1 day

Post Go-Live Support 14 days

Post Go-Live Support 14 days Note: This is high level plan subject to change during Business Blue Print Phase 0 days