on 11-10-2007 12:18 AM
Hi
The org I work for are going to upgrade BW from V3.5 to V7, and are currently looking at BI/IP for a stream of work.
They use statistical WBS elements where the 'real' posting is in a cost centre.
From a planning perspective, how can a 'double-up' on planning be avoided - ie, both the WBS and the cost centre.
Can statistical postings be excluded somehow from planning?
Thanks in advance for assistance
Hi,
I think the simple way to exclude the stastical WBS postings from planning can be to restrict your planning levels with stastical WBS '#'. Is this not suitable in your case?
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.