Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Request must still be Approved - ChaRM

Hi all,

I am unit testing ChaRM and I am getting an error when I try to bring the changes into production.

<b>Error</b>

Transport control program tp ended with error code 0250

Message no. XT200

Diagnosis

An error occurred when executing a tp command.

Command: IMPORT ALL SMD clires100 proj=SOME pf=/usr/sap/tra

Return code: 0250

Error text: inactive entries found in buffer

Request: ALL

System Response

The function terminates.

Procedure

Correct the error and execute the command again if necessary.

<b>Cause:</b>

In STMS the transports for my Normal Correction and Test Message have a icon that says<b> "Request must still be Appoved"</b>.

My Normal Correction's status is Tested Successfully.

I used a Test Message to fix a problem with the Normal Correction and its status is Confirmed

The Maintenance Cycyle's status is Go-live.

What am I doing wrong?

regards,

Jason

Former Member
Not what you were looking for? View more on this topic or Ask a question