PO Requirement Date

Here is the issue -- in this case related to production orders, but effects all items.

Production order is created with commit date of November 15; start date is November 14 based on routing times; lead time for the unit is 13 days. The components of the unit show purchasing that the goods are required on November 14 when in reality the unit can begin production anywhere from 13 days to 1 day before it is due.

We must be missing something in the set up of our components.

How can we set the components up so that purchasing sees the requirement with some sort of buffer before it is actually due.

We know that we can look at scheduling floats, but we are looking for other alternatives.

Any assistance would be greatly appreciated.

Regards,

Kristine