Hi Every one.

Where can we control ATP with respect to SD and MM respectively.

Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi There,

Availability check control in SD will be link as requirement per item material. It's controlled by either schedule line item category or requirement type.

Basically, the system confirms everything if the Avlb check is not activated, the Avlb check must be activated at:

a. material master (MM02), maintain a checking group that allows ATP and

b. determine a requirements class and a schedule line category that allow ATP.

Regards,

Gumanti