I have created a batch job to run MRP, I have noticed that the MRP run is not planning some materials!

I have a material with a contstant demand, this is called off via schedule lines, if I run the Batch Job MRP I get no planning, if I run Single item Multi level it works.

The Planning time fence is OK, does any one have any suggestions?

Kind regards


What do you mean by "called off via schedule lines"?

Please check the MRP parameters in both transaction MDBT and MD02/MD01

Scope of planning


Processing key

Create purchase req.

Schedule lines

Create MRP list

Planning mode


Planning date

Display material list

Parallel processing

User exit key

User exit parameters

Am sure there will be difference.