Check of operation sequence in order

Former Member
0 Kudos

Hi all,

I don't want to check of operation sequence in order. so how can I do this? Are there any customizing for this case?

Best regards,

Hilal Çakır

email : hcakir0507@hotmail.com

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Make the following changes in control key or use the control key which have this setting

In OPJ8, for a control key

Confirmation = Confirmation possible but not necessary

In OPK4, for a plantb and production order type combination in Generally valid settings tab page -

Checks sub page

operation sequence = set operation sequence is not checked

With this setting it will work

Former Member
0 Kudos

thank you. I tried it and it was successful.

Former Member
0 Kudos

reward and close the thread.

Answers (2)

Answers (2)

Former Member
0 Kudos

thank you.

Former Member
0 Kudos

Dear Hilal,

Do u meant to say, during order Confirmation , donot want to consider sequence of opeartion, if not could please explain more elaborate.

regards

pradeep

Former Member
0 Kudos

hi ,

Yes , I mean to say order confirmation.

hilal

Former Member
0 Kudos

Hi,

1.if want to confirm last opeartion without confirming previous operations, set "milstone conformation "control Key at last operation and set Control key has Cofirmation = "Confirmation possible but not necessary" for Previous opeartion.(Define control key OPJ8)

2 Set opeartion sequence = Operation sequence not checked In for ur ordre type/plant combination in opK4

regards

pradeep