on 11-09-2007 1:53 AM
Hi,
The example
WBS00
WBS01 actual start date = 2007/11/07 (Minimum of {2007/11/07, 2007/11/07, 2007/11/09} )
- Activity1 actual start date = 2007/11/07
- Activiy2 actual start date = 2007/11/07
- Activiy3 actual start date = 2007/11/09
WBS10
I dont know if there a mechanism to automatically update Actual Start Date of WBS01 when Actual Start Date of activity1 or activity2 of activity3?
The problem which Im facing:
I create a project from cProject.
PS is generated & assigned automatically when indicator status of cProject flag to transfer is set.
Easy cost planning for this project is generated correctly too.
I used CAT2 (time sheet) to input time for an activity. Use CAT7 to transfer to CO (result is oK). Use report DPR_CATS_CPR_TRANSF to transfer confirmation time to cProject (result is oK).
The measurement method is 20-80 (for calculating POC).
Because the actual start date of WBS of this activity is not updated so POC is zero. May I have to input actual start date for the WBS manually?
Dear Long
I'm afraid that u may have to manually enter the actual start of the respective WBS element, as SAP works on the principle - actual start of the subordinate activity can be different from the actual start of the WBS Element.
Regards
Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
11 | |
6 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.