cProject + Progress report (Earned value)

Former Member
0 Kudos

Hi,

The example

WBS00

WBS01 actual start date = 2007/11/07 (Minimum of {2007/11/07, 2007/11/07, 2007/11/09} )

- Activity1 actual start date = 2007/11/07

- Activiy2 actual start date = 2007/11/07

- Activiy3 actual start date = 2007/11/09

WBS10

I don’t know if there a mechanism to automatically update Actual Start Date of WBS01 when Actual Start Date of activity1 or activity2 of activity3?

The problem which I’m facing:

I create a project from cProject.

PS is generated & assigned automatically when indicator status of cProject flag to transfer is set.

Easy cost planning for this project is generated correctly too.

I used CAT2 (time sheet) to input time for an activity. Use CAT7 to transfer to CO (result is oK). Use report DPR_CATS_CPR_TRANSF to transfer confirmation time to cProject (result is oK).

The measurement method is 20-80 (for calculating POC).

Because the actual start date of WBS of this activity is not updated so POC is zero. May I have to input actual start date for the WBS manually?

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear Long

I'm afraid that u may have to manually enter the actual start of the respective WBS element, as SAP works on the principle - actual start of the subordinate activity can be different from the actual start of the WBS Element.

Regards

Murali