Phase UPGRADE/EUIM: START OF PHASE SHADOW_IMPORT_UPG1 too long

Hello

We're upgrade our 4.70 to ECC 6.00 (Development) and the process it's being so long, the phase UPGRADE/EUIM: START OF PHASE SHADOW_IMPORT_UPG1 started this morning at 9:15 and now it's 20:30 and it continues doing something.

We have a 550 Power5+ with 2 processors and 15GB of RAM.

We see that the R3trans process is consuming only the 10% of the CPU. Is it possible to make this job more efficient?

Thank you in advanced.

Rubén García.