Dear gurus,
I did a 101 movement in MIGO and the system did a 543 for the components to relieve the material from vendor but I can't see the material at our storage location.
With best regards and Happy Diwali to all my friends.
Syed
Hi Syed,
Subcontracting PO concept itself is this -
You will provide some components to vendor (using 541 mvt type before hand)
Vendor completes manufacture of the finished product for you. This FG you will enter as item to be procured from the vendor in the pO with item category L
The bom maintained in CS03 provides components list to be sent to vendor (you may find within the PO at the item -->Material Data tab...click the higherarchy icon on the right side within this tab.
Now, when you receive finished product from your subcon vendor, it posts with 101 for FG and components are consumed automatically with 543. Hope, it is clear now...
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Gopala,
In MIGO, storage location field is greyed out. What is happening is since in PR cost center is defined for the parent material (subcontracted material), in GR the material is expensed out to cost center. I want to receive the material in defined (MRP) storage location. I have looked in OMJX and storage location is input.
I would appreciate if someone could provide a specific answer to my query.
Thanks
Syed