How to specify that one of the operation should not be costed.
Through control key I can do this,any other method.
Thanks
PPC
Hi
There is a costiong relevency field in operation detail screen .
you can deactivate the same.
Regards
YMREDDY
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
1)In routing opration detailed screen, make the opration not relavent to costing(remove costing rel = X and make it space
2)customizse the control key in OP67, for a control key in indicators remove the cost tick, assign this control key for the oprations in routing for which you donot want cost.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
If you want to restrict only for particular operation then customize using control key only.
cheers
SAN
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.