Hi all,

we are in Netweaver 2004s SP 9, we dont have schedule the adapter in Communication Channel monitoring. so we want to upgrade to SP10.

1)Can any one please tell me the process to upgrade the support package?

2) which one must i upgrade ABAP stack or JAVA stack if i want get the schedule the adpter functionality?

Answer will be rewarded.

Kiran.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Make sure you patch to the latest versions (Adapter framework) after upgrading SPS release, as the scheduling is still quite buggy in places. I'm on 7.0 sps 12 and the patches offer a number of fixes for scheduling!

Cheers

James.

prateek
Active Contributor
0 Kudos

1. Download the support package https://websmp205.sap-ag.de/swdc -> SAP Software Distribution Center -> Download ->

Support Packages and Patches -> Entry by Application Group -> SAP NetWeaver -> SAP NETWEAVER -> SAP NETWEAVER 04 -> Support Package Stacks ->

2. Java. But it is recommended to have same SP levels for both the stacks

Regards,

Prateek

Former Member
0 Kudos

You need to upgrade all components to SP10 to ensure consistency, although i would recommend SP12. I have had lots of issues with SP10.