on 11-06-2007 2:22 PM
Hi All,
I am working on ECC6.0. i have scheduled DB13 jobs and getting failed. Now i want to cancel the jobs i didnot find any cancel option. please suggest me how to cancel the jobs.
thnaks,
praveen.
Hi Praveen,
DB13 is the scheduler, so you can't cancel something which already running through DB13.
You can kill any process with tx SM50 or find the PID of the process and kill it from OS level.
Best way would be using the 'BRTOOLS' rather than doing it on the OS level
Reward points if useful.
Best regards,
Loukas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Go to DB13 , select the next occurrence of the job and delete this will delete the job from your DBA planning calendar
Thanks
Prince Jose
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.