update of inhouse production time w.r.t Routing timings

Hi PP gurus

This is regarding the material master update for inhouse production time with Routings lead times.

I know we can do it via scheduling the same in routings first and then run the CA96 to change the material master inhouse production time (lot dependent )

Is there any way to do the same for Mass numbers of materials.

As in my current project it is mandatory to update the queue time on daily basis in work centers and update the Relenishment lead time in material master everyday to give a realislic quote to customers..

thanks in advance