HI

Where can you define the settings for MRP to exclude Quality Inspection stock from the total plant stock planning run, e.g. unrestricted stock only?

regards

AJ

Accepted Solutions (1)

Accepted Solutions (1)

Lakshmipathi
Active Contributor
0 Kudos

Hi AJ

In Material Master, select "Quality Management" and press "Insp setup" tab.

A screen will appear wherein you can find your QM people would have assigned various inspection types under the tab "inspection types". Whichever you dont want, delete it and save the material master.

Thanks

G. Lakshmipathi

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

In Material Master