hi,

what is the best way to maintain cost center and profit center hierarchy. can we transport it from dev to quality or they are client independent. i have started to maintain the heirarchy in dev.( customizing client - no master data)

please let me know.

thanks.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Cost Center.. Proces flow...

1. Create a cost center, as described in Processing Master Data.

2. To lock the representative cost center against manual postings, choose Indicators in the Cost Centers basic screen and set the lock indicators.

3. In cost center group maintenance or in the standard hierarchy, enter the representative cost center in the report information. Choose Extras --> Report information in the Change Cost Center Group screen, and enter the representative cost center in the Report Information dialog box.

Thank u.. assign points if useful..my notes...

Dasharathi

Former Member
0 Kudos

You can transport them. Transport is the better way. Use OKE6.

Assign points if helpful

JozsefSzikszai
Active Contributor
0 Kudos

hi Win_0179,

pls. check <b>transaction OKE6</b> to transport many things from dev to test and to prod system.

hope this helps

ec