MM-IM-Update Control

Hi everyone,

I have a problem with movement type 562 - E.

The system tells me that this movement is not updated in the "update control" table for the movement (562_XE_ _ E).

I go to transaction OMJJ but hte problem is that I cannot add any entry in this table... and when I try to create a new movement type to see if I have any possiblity, it just copies the entrie of the reference movement and I still don't have the option of inserting any entry.

Does anyone can help me ?

Thank you very much.

Regards,

Former Member
Former Member replied

Hi Remi,

Maintain new entries from SM30, via view: V_156SC_VC

OMJJ doesn't have this New Entries feature. However, you can enter from view above. I did several like this...Go ahead.