Hi
Does anyone know how this transaction operates in respect of releasing sales order ,when the only available stock is in safety stock, and the sales order is at a later confirmed date than earlier sales orders?
js
Hi John:
This is what we do, we go to the transaction and double click on the MRP element highlighted in blue from where we want to take the stock (reservation, safety stock).
then at the bottom of the screen I'd remove the amount in the 'committed' box. From there I'd then go back to the sales order and do an availability check.
Give that a try.
Regards
Aaon